C45 over two visits, charged on the volume used

2.96 m³

used, against 3 m³ ordered

Location
Winford
Application
New MOT bay ramp and sub-base
Concrete
C45
Volume
8.2 m³, then 2.96 m³
Delivery
Two visits
  1. 01

    The job

    C45 concrete for a new MOT bay, supplied over two visits.

  2. 02

    First visit

    Palmix supplied the concrete for the ramp sub-base. The job needed 8.2 m³, more than was originally ordered.

  3. 03

    Second visit

    The contractor ordered 3 m³. The delivery ticket showed 2.96 m³ used.