Case study · Burnham-on-Sea

Subfloor, Burnham-on-Sea

1.5 m³ poured through a window in under 10 minutes

< 10 min

to pour 1.5 m³ through a window

Location
Burnham-on-Sea
Application
New subfloor in a property conversion
Concrete
C20
Volume
1.5 m³
Delivery
Poured through a window
  1. 01

    The job

    A seaside property in Burnham-on-Sea was being converted into rental apartments and needed a new concrete subfloor.

  2. 02

    What was needed

    The builders wanted to pour through a window rather than barrow the concrete in, so the window was removed to fit the chute.

  3. 03

    On the day

    1.5 m³ of C20 was placed through the window in under 10 minutes, without barrowing. The contractor gave Palmix positive feedback afterwards.